POWER TRANSFORMER | DISTRIBUTION TRANSFORMER | TRANSFORMER DESIGN | TRANSFORMER PRINCIPLES | TRANSFORMER THEORY | TRANSFORMER INSTALLATION | TRANSFORMER TUTORIALS
SINGLE PHASE PAD MOUNTED TRANSFORMER PARTS BASIC INFORMATION AND TUTORIALS
Parts Of Pad-Mounted Single-Phase Distribution Transformers
Single-phase pad mounted distribution transformers are used in underground distribution systems where it is preferable to have underground rather than overhead distribution. An example of a single-phase, pad mounted distribution transformer with its cover raised is shown in below.
Single-phase, pad-mounted transformers are manufactured with ratings from 10 to 167 kVA. All of these distribution transformers are oil-insulated, self-cooled, and made with loop or radial feed. They can meet or exceed ANSI and NEMA standards.
Pad-mounted distribution transformers are enclosed in steel tamper-resistant protective cases designed with low profiles. They are usually painted green to blend in
Submersible single-phase distribution transformers
Single-phase submersible underground transformers are enclosed in round vertical stainless steel tanks that are hermetically sealed for protection against repeated flooding and/or immersion. The terminals, ground pads, and nameplates are mounted on the covers for easy access from ground level.
These transformers are made in ratings of 25 to 167 kVA. Where submersible transformers are to be installed in a trench that is not subject to repeated flooding or immersion, they are enclosed in stainless steel tanks. Their terminals, ground pads, and nameplates are mounted on their covers.
POWER TRANSFORMER RATING, LOSSES AND EFFICIENCY BASIC INFORMATION
Power transformer capacity is rated in kilovolt-amperes (kVA). The output rating for a transformer is determined by the maximum current that the transformer can withstand without exceeding its stated temperature limits.
Power in an AC circuit depends on the power factor of the load and the current, so if any AC electrical equipment is rated in kilowatts, a power factor must be included to make its power rating meaningful. To avoid this, transformers and most AC machines are rated in kVA, a unit that is independent of power factor.
In addition to its kVA rating, the nameplates of transformers typically include the manufacturer’s type and serial number, the voltage ratings of both high- and low voltage windings, the rated frequency, and the impedance drop expressed as a percentage of rated voltage. Some nameplates also include an electrical connection diagram.
Power transformers are generally defined as those used to transform higher power levels than distribution transformers (usually over 500 kVA or more than 67 kV). The kVA terminal voltages and currents of power transformers, defined in ANSI C57.12.80, are all based on the rated winding voltages at no-load conditions.
However, the actual primary voltage in service must be higher than the rated value by the amount
of regulation if the transformer is to deliver the rated voltage to the load on the secondary.
TRANSFORMER LOSSES AND EFFICIENCY
The efficiency of all power transformers is high, but efficiency is highest for large transformers operating at 50 to 100 percent of full load. However, some losses are present in all transformers. They are classified as copper or I2R losses and core losses.
Copper losses, also called load losses, are proportional to the load being supplied by the transformer. These losses can be calculated for a given load if the resistances of both windings are known. As in generators and motors, the core loss is due to eddy-current induction loss and hysteresis (molecular friction) loss, caused by the changing polarity of the applied AC.
If the cores are laminated from low-loss silicon steel, both eddy-current and hysteresis losses will be reduced. Nevertheless, well-designed transformers in all frequency and power ranges typically have efficiencies of 90 percent or more.
THREE-PHASE DISTRIBUTION TRANSFORMERS PARTS BASIC INFORMATION
WHAT ARE THE PARTS OF THREE PHASE DISTRIBUTION TRANSFORMERS (SINGLE UNIT)
A three-phase overhead distribution transformer is shown in the figure below. Where pole mounted overhead distribution is used to supply three-phase power, three-phase transformers occupy less space than a bank of transformers, and they weigh less.
Moreover, the cost of installation and maintenance is lower for a three-phase overhead transformer than for a bank of three single-phase units.
Three-phase overhead transformers are made with ratings from 30 to 300 kVA. Primary voltages range from 4.16 to 34.5 kV, and secondary voltages range from 120 to 480 V.
The basic impulse level (BIL) ratings are 45 to 150 kV. They are available with wye, delta, or T–T connections. These transformers have four output connections, X0, X1, X2, and X3, and their cases are filled with electrical-grade mineral oil.
These transformers are manufactured in ratings from 45 to 7500 kVA with high-voltage ratings from 2.4 to 46 kV. The standard connections are delta–wye, grounded wye–wye, delta–delta, wye–wye, and wye delta.
The transformers are housed in steel cabinets with front-opening, three-point latching steel doors. As in the overhead transformers, the cases of pad-mounted transformers are filled with electrical-grade mineral oil.
A three-phase overhead distribution transformer is shown in the figure below. Where pole mounted overhead distribution is used to supply three-phase power, three-phase transformers occupy less space than a bank of transformers, and they weigh less.
Moreover, the cost of installation and maintenance is lower for a three-phase overhead transformer than for a bank of three single-phase units.
Three-phase overhead transformers are made with ratings from 30 to 300 kVA. Primary voltages range from 4.16 to 34.5 kV, and secondary voltages range from 120 to 480 V.
The basic impulse level (BIL) ratings are 45 to 150 kV. They are available with wye, delta, or T–T connections. These transformers have four output connections, X0, X1, X2, and X3, and their cases are filled with electrical-grade mineral oil.
These transformers are manufactured in ratings from 45 to 7500 kVA with high-voltage ratings from 2.4 to 46 kV. The standard connections are delta–wye, grounded wye–wye, delta–delta, wye–wye, and wye delta.
The transformers are housed in steel cabinets with front-opening, three-point latching steel doors. As in the overhead transformers, the cases of pad-mounted transformers are filled with electrical-grade mineral oil.
YY AUTO 3Ø / NEUTRAL = PRIM YES-SEC NO AUTO TRANSFORMER CONNECTION AND DIGRAM
WHERE USED
For increasing voltage at the end of
lines or to step up voltage where line extensions are being added to
existing lines, such as from 6900 VAC to 7200 VAC. Cost per kva
output is less than a two-winding transformer; losses are low,
regulation is good, and exciting current is low. Voltage
transformation greater than 3 to 1 is not recommended.
FOR POWER FROM A 3Ø, 4W SYSTEM
When the ratio of transformation from
the primary to secondary voltage is small, the most economical way of
stepping down the voltage is by using autotransformers as shown. For
the application, it is necessary that the neutral of the auto
transformer bank be connected to the system neutral. Brand circuits
shall not be supplied by autotransformers.
CAUTION
Susceptive to burnouts if the system
impedance is not great enough to limit the short-circuit current to
20 to 25 times the transformer-rated current. The primary neutral
should be tied firmly to the system neutral; otherwise, excessive
voltages may develop on the secondary side.
RATING & FUNCTION
A considerable saving in cost may often
be experienced by using autotransformers instead of two-winding
transformers. When it is desired to affect a small change in voltage,
or where both high and low voltages are low, there is usually no
reason why an autotransformer cannot be used as successfully as a
two-winding transformer.
Autotransformers should not, except
under special conditions, be used where the difference between the
high-voltage and low-voltage ratings is great. This is because the
occurrence of grounds at certain points will subject the insulation
on the low-voltage circuit to the same stress as the high-voltage
circuit.
Autotransformers are rated on the basis
of output KVA rather than the transformer KVA. Efficiencies,
regulation and other electrical characteristics are also based on
output rating.
DELTA – DELTA (ΔΔ) CLOSED / NEUTRAL = PRIM NO-SEC YES TRANSFORMER CONNECTION TUTORIALS AND BASIC INFORMATION
WHERE USED
For supplying three-phase, 240-volt
loads with small amounts of 120/240-volt, single-phase load. No
problem from third harmonic overvoltage or telephone interference.
With a disabled unit, bank can be reconnected in open-delta for
emergency service.
DELTA-DELTA FOR LIGHTING AND POWER
This connection is often used to supply
a small single-phase lighting load and three-phase power load
simultaneously. As shown is diagram, the mid-tap of the secondary of
one transformer is grounded.
Thus, the small lighting load is
connected across the transformer with the mid-tap and the ground wire
common to both 120 volt circuits. The single-phase lighting load
reduces the available three-phase capacity. This connection requires
special watt-hour metering and is not available from all utilities.
DIAGRAM
BANK RATING
The transformer with the mid-tap
carries 2/3 of the 120/240-volt, single-phase load and 1/3 of the
240-volt, three-phase load. The other two units each carry 1/3 of
both the 120/240- and 240-volt loads.
CAUTION
High circulating currents will result
unless all units are connected on same regulating taps and have same
voltage ratios. Bank rating is reduced unless matching impedance
transformers are used. The secondary neutral bushing can be grounded
on only one of the three transformers.
IMPEDANCE
When three transformers are operated in
a closed-delta bank, care should be taken to make certain the
impedances of the three units are practically the same. Transformers
having more than 10% difference in impedance rating should not be
operated together in a closed-delta bank unless a reactor is used to
increase the impedance of the unit having the lower impedance rating
to a value equal to the other units.
If the voltage ratio of all three of
the transformers is not the same, there will be a voltage tending to
circulate current inside the delta. The current will be limited by
the impedance of the three transformers considered as a series
circuit.
It is a good practice, before applying
voltage to three transformers in closed delta, to insert a fuse wire
between the leads coming from the high-voltage bushings of two
transformers closing the delta bank. The fuse wire should be of
sufficient size to carry the exciting current of the transformers.
The use of this fuse wire offers a very
simple means of making certain the transformers have the proper
polarity.
This connection should not be used with
CSP transformers if used to supply a combined three-phase and
three-wire single-phase load due to unequal voltage division of
single-phase load when the tapped transformer breaker is opened.
HIGH-LEG MARKING
NEC 2002: 110.15 High-Leg Marking.
On a 4-wire, delta-connected system
where the midpoint of one phase winding is grounded to supply
lighting and similar loads, the conductor or busbar having the higher
phase voltage to ground shall be durably and permanently marked by an
outer finish that is orange in color or by other effective means.
Such identification shall be placed at each point on the system where
a connection is made if the grounded conductor is also present.
NEC 2002 Handbook:
Added for the 2002 Code, this section
now contains a requirement that appeared in 384-3(e) of the 1999 NEC.
This requirement was moved to Article 110, where the application
becomes a more general requirement.
The high leg is common on a
240/120-volt 3-phase, 4-wire delta system. It is typically designated
as “B phase.” The high-leg marking is required to be the color
orange or other similar effective means and is intended to prevent
problems due to the lack of complete standardization where metered
and non-metered equipment are installed in the same installation.
Electricians should always test each phase relative to ground with
suitable equipment to determine exactly where the high leg is located
in the system.
ARRANGEMENT OF BUSBARS AND
CONDUCTORS
NEC 2002: 408.3 / Support and
Arrangement of Busbars and Conductors / (E) Phase Arrangement
The phase arrangement on 3-phase buses
shall be A, B, C from front to back, top to bottom, or left to right,
as viewed from the front of the switchboard or panelboard.
The B phase shall be that phase having
the higher voltage to ground on 3-phase, 4-wire, delta-connected
systems. Other busbar arrangements shall be permitted for additions
to existing installations and shall be marked.
Exception: Equipment within the same
single section or multisection switchboard or panelboard as the meter
on 3-phase, 4-wire, delta-connected systems shall be permitted to
have the same phase configuration as the metering equipment.
FPN: See 110.15 for requirements on
marking the busbar or phase conductor having the higher voltage to
ground where supplied from a 4-wire, delta-connected system.
NEC 2002 Handbook:
The high leg is common on a
240/120-volt, 3-phase, 4-wire delta system. It is typically
designated as “B phase.” Section 110.15 requires the high-leg
marking to be the color orange or other similar effective means of
identification. Electricians should always test each phase to ground
with suitable equipment in order to know exactly where this high leg
is located in the system.
The exception to 408.3(E) permits the
phase leg having the higher voltage to ground to be located at the
right-hand position (C phase), making it unnecessary to transpose the
panelboard or switchboard busbar arrangement ahead of and beyond a
metering compartment. The exception recognizes the fact that metering
compartments have been standardized with the high leg at the right
position (C phase) rather than in the center on B phase.
See also 110.15, 215.8, and 230.56 for
further information on identifying conductors with the higher voltage
to ground. Other busbar arrangements for making additions to existing
installations are permitted by 408.3(E).
COMMISSIONING, MAINTENANCE AND REPAIR OF POWER TRANSFORMER BASIC INFORMATION
Commissioning
Small power transformers can be
transported to site complete with oil, bushings, tap changers and
cooling equipment. It is then a relatively simple matter to lift them
onto a pole or plinth and connect them into the system.
Large transformers are subject to
weight restrictions and size limitations. When they are moved by road
or rail and it is necessary to remove the oil, bushings, cooling
equipment and other accessories to meet these limitations. Very large
transformers are usually carried on custom-built transporters.
Once a transformer of this size arrives
on site, it must be lifted or jacked onto its plinth for re-erection.
In some cases with restricted space it may be necessary to use
special techniques, such as water skates to maneuver the transformer
into position.
When the transformer has been erected
and the oil filled and reprocessed, it is necessary to carry out
commissioning tests to check that all electrical connections have
been correctly made and that no deterioration has occurred in the
insulation system.
These commissioning tests are selected
from the routine tests and usually include winding resistance and
ratio, magnetizing current at 440 V, and analysis of oil samples to
establish breakdown strength, water content and total gas content. If
oil samples indicate high water content then it may be necessary to
dry the oil using methods addressed in the following section.
Maintenance
Transformers require little maintenance
in service, apart from regular inspection and servicing of the OLTC
mechanism. The diverter contacts experience significant wear due to
arcing, and they must be replaced at regular intervals which are
determined by the operating regime.
For furnace transformers it may be
advisable to filter the oil regularly in a diverter compartment in
order to remove carbon particles and maintain the electrical
strength.
The usual method of protecting the oil
breather system in small transformers is to use silicone gel
breathers to dry incoming air; in larger transformers refrigerated
breathers continuously dry the air in a conservator. Regular
maintenance (at least once a month) is necessary to maintain a silica
gel breather in efficient working order.
If oil samples indicate high water
content then it may be necessary to dry the oil using a heating
vacuum process. This also indicates high water content in the paper
insulation and it may be necessary to redry the windings by applying
a heating and vacuum cycle on site, or to return the transformer to
the manufacturer for reprocessing or refurbishment.
An alternative procedure is to pass the
oil continuously through a molecular sieve filter. Molecular sieves
absorb up to 40 per cent of their weight of water.
Diagnostics and repair
In the event of a failure, the user
must first decide whether to repair or replace the transformer. Where
small transformers are involved, it is usually more economic to
replace the unit. In order to reach a decision, it is usually
necessary to carry out diagnostic tests to identify the number of
faults and their location.
Diagnostic tests may include the
surveillance tests, and it may also be decided to use acoustic
location devices to identify a sparking site, low-voltage impulse
tests to identify a winding fault and frequency response analysis of
a winding to an applied square wave to detect winding conductor
displacement.
If the fault is in a winding, it
usually requires either replacement of the winding in a repair
workshop or rewinding by the manufacturer, but many faults external
to the windings, such as connection or core faults can be corrected
on site.
Where a repair can be undertaken on
site it is essential to maintain dry conditions in the transformer by
continual purging using dry air. Any material taken into the tank
must be fully processed and a careful log should be maintained of all
materials taken into and brought out of the tank.
When a repair is completed, the
transformer must be re-dried and re-impregnated, and the necessary
tests carried out to verify that the transformer can be returned to
service in good condition.
IN SERVICE TESTING OF POWER TRANSFORMERS BASIC INFORMATION
Two types of in-service testing are
used. Surveillance testing involves periodic checks, and condition
monitoring offers a continuous check on transformer performance.
(a) Surveillance testing – oil
samples
When transformers are in operation,
many users carry out surveillance testing to monitor operation. The
most simple tests are carried out on oil samples taken on a regular
basis.
Measurement of oil properties, such as
breakdown voltage, water content, acidity, dielectric loss angle,
volume resistivity and particle content all give valuable information
on the state of the transformer.
DGA gives early warning of
deterioration due to electrical or thermal causes, particularly
sparking, arcing and service overheating.
Analysis of the oil by High-Performance
Liquid Chromatography (HPLC) may detect the presence of furanes or
furfuranes which will provide further information on moderate
overheating of the insulation.
(b) On-line condition monitoring
Sensors can be built into the
transformer so that parameters can be monitored on a continuous
basis. The parameters which are typically monitored are winding
temperature, tank temperature, water content, dissolved hydrogen,
partial discharge activity, load current and voltage transients.
The data collection system may simply
gather and analyse the information, or it may be arranged to operate
alarms or actuate disconnections under specified conditions and
limits which represent an emergency.
Whereas surveillance testing is carried
out on some distribution transformers and almost all larger
transformers, the high cost of on-line condition monitoring has
limited the application to strategic transformers and those
identified as problem units.
As the costs of simple monitoring
equipment fall, the technique should become more applicable to
substation transformers.
TRANSFOMER POWER FACTOR/ CAPACITANCE MEASUREMENT BASIC INFORMATION
Two methods are used to make power
(dissipation) factor and capacitance measurements. The first is the
grounded specimen test (GST), where current, watts, and capacitance
of all leakage paths between the energized central conductor and all
grounded parts are measured.
Measurements include the internal core
insulation and oil as well as leakage paths over the insulator
surfaces. The use of a guard circuit connection can be used to
minimize the effects of the latter.
The second method is the ungrounded
specimen test (UST), where the above quantities are measured between
the energized center conductor and a designated ungrounded test
electrode, usually the voltage or test tap.
The two advantages of the UST method
are that the effects of unwanted leakage paths, for instance across
the insulators, are minimized, and separate tests are possible while
bushings are mounted in apparatus.
Standards recommend that power factor
and capacitance measurements be made at the time of installation, a
year after installation, and every three to five years thereafter. A
significant increase in a bushing’s power factor indicates
deterioration of some part of the insulating system.
It may mean that one of the insulators,
most likely the air-end insulator, is dirty or wet, and excessive
leakage currents are flowing along the insulator. A proper reading
can be obtained by cleaning the insulator.
On the other hand, a significant
increase of the power factor may also indicate deterioration within
the bushing. An increase in the power factor across the C1 portion,
i.e., from conductor to tap, typically indicates deterioration within
the core.
An increase across the C2 portion of a
bushing using a core, i.e., from tap to flange, typically indicates
deterioration of that part of the core or the bushing oil. If power
factor doubles from the reading immediately after initial
installation, the rate of change of the increase should be monitored
at more frequent intervals.
If it triples, then the bushing should
be removed from service. An increase of bushing capacitance is also a
very important indicator that something is wrong inside the bushing.
An excessive change, on the order of 2
to 5%, depending on the voltage class of the bushing, over its
initial reading probably indicates that insulation between two or
more grading elements has shorted out. Such a change in capacitance
is indication that the bushing should be removed from service as soon
as possible.
POWER TRANSFORMER THERMAL STABILITY TEST BASIC INFORMATION
Capacitive leakage currents in the
insulating material within bushings cause dielectric losses.
Dielectric losses within a bushing can be calculated by the following
equation using data directly from the nameplate or test report:
Pd = 2 pi f C V2 tan ��
where
Pd = dielectric losses, W
f = applied frequency, Hz
C = capacitance of bushing (C1), F
V = operating voltage, rms V
tan �� = dissipation
factor, p.u.
A bushing operating at rated voltage
and current generates both ohmic and dielectric losses within the
conductor and insulation, respectively. Since these losses, which
both appear in the form of heat, are generated at different locations
within the bushing, they are not directly additive.
However, heat generated in the
conductor influences the quantity of heat that escapes from within
the core. A significant amount of heat generated in the conductor
will raise the conductor temperature and prevent losses from escaping
from the inner surface of the core.
This causes the dielectric losses to
escape from only the outer surface of the core, consequently raising
the hottest-spot temperature within the core.
Most insulating materials display an
increasing dissipation factor, tan ��, with higher
temperatures, such that as the temperature rises, tan ��
also rises, which in turn raises the temperature even more. If this
cycle does not stabilize, then tan �� increases
rapidly, and total failure of the insulation system ensues.
Bushing failures due to thermal
instability have occurred both on the test floor and in service. One
of the classic symptoms of a thermal-stability failure is the high
internal pressure caused by the gases generated from the
deteriorating insulation.
These high pressures cause an
insulator, usually the outer one because of its larger size, either
to lift off the flange or to explode. If the latter event occurs with
a porcelain insulator, shards of porcelain saturated with oil become
flaming projectiles, endangering the lives of personnel and causing
damage to nearby substation equipment.
Note from Equation that the operating
voltage, V, particularly influences the losses generated within the
insulating material. It has been found from testing experience that
thermal stability only becomes a factor at operating voltages 500 kV
and above.
POWER TRANSFORMER DIELECTRIC TESTS TYPES BASIC INFORMATION
Low-Frequency Tests
There are two low-frequency tests:
1. Low-frequency wet-withstand voltage
test
2. Low-frequency dry-withstand voltage
test
Low-Frequency Wet-Withstand Voltage
Test — The low-frequency wet-withstand voltage test is applied
on bushings rated 242 kV and below while a waterfall at a particular
precipitation rate and conductivity is applied. The values of
precipitation rate, water resistivity, and the time of application
vary in different countries.
American standard practice is a
precipitation rate of 5 mm/min, a resistivity of 178 ohm-m, and a
test duration of 10 sec, whereas European practice is 3 mm/min, 100
ohm��m, and 60 sec, respectively.
If the bushing flashes over externally
during the test, it is allowed that the test be applied one
additional time. If this attempt also flashes over, then the test
fails and something must be done to modify the bushing design or test
setup so that the capability can be established.
Low-Frequency Dry-Withstand Voltage
Test — The low-frequency dry-withstand test was, until
recently, made for a 1-min duration without the aid of
partial-discharge measurements to detect incipient failures, but
standards currently specify a one-hour duration for the design test,
in addition to partial-discharge measurements.
The present test procedure is:
Partial discharge (either
radio-influence voltage or apparent charge) shall be measured at 1.5
times the maximum line-ground voltage. Maximum limits for partial
discharge vary for different bushing constructions and range from 10
to 100 ��V or pC.
A 1-min test at the dry-withstand
level, approximately 1.7 times the maximum line-ground voltage, is
applied. If an external flashover occurs, it is allowed to make
another attempt, but if this one also fails, the bushing fails the
test. No partial-discharge tests are required for this test.
Partial-discharge measurements are
repeated every 5 min during the one-hour test duration at 1.5 times
maximum line-ground voltage required for the design test. Routine
tests specify only a measurement of partial discharge at 1.5 times
maximum line-ground voltage, after which the test is considered
complete.
Bushing standards were changed in the
early 1990s to align with the transformer practice, which started to
use the one-hour test with partial-discharge measurements in the late
1970s. Experience with this new approach has been good in that
incipient failures were uncovered in the factory test laboratory,
rather than in service, and it was decided to add this procedure to
the bushing test procedure.
Also from a more practical standpoint,
bushings are applied to every transformer, and transformer
manufacturers require that these tests be applied to the bushings
prior to application so as to reduce the number of bushing failures
during the transformer tests.
POWER TRANSFORMER AUTOMATIC TAP CHANGER CONTROLS BASIC INFORMATION
How Transformer Tap Changer Control
Works?
The tap-changing mechanism is usually
motor-driven and can be controlled manually and automatically. In the
automatic mode, the output voltage of the transformer is compared to
a reference voltage and a raise/lower signal is sent to the tap
changer motor when the output voltage falls outside a specified band,
called a dead band.
The dead band must not be smaller than
the voltage between taps; otherwise, it will ‘‘hunt’’
endlessly and burn up the tap changer. The dead band must not be too
wide, however, because the purpose of voltage regulation will be
defeated.
Ordinarily, the dead band is set to a
voltage between two and three tap increments. With the tap voltage
typically around 1% of the nominal secondary voltage, this provides
regulation within a 2–3% range.
If two or more transformers with load
tap changers are connected in parallel, then it is important that all
transformers operate at the same transformer turns ratio; otherwise,
excessive circulating KVAR results. The way this is implemented is to
have the tap changer on one of the parallel transformers control
voltage as the lead tap changer, with the other tap changers as the
followers.
Circuitry is installed on the followers
to sense the direction of reactive power flow through each
transformer. If too much reactive power is flowing from the primary
to the secondary, then its secondary taps are lowered.
If too much reactive power is flowing
from the secondary to the primary, then secondary taps are raised.
Appropriate dead bands are established to prevent the LTCs from
hunting and to limit interactions among the tap changer controls.
One such control scheme, called a
load-balancing method, is depicted in Figure 6.16 for three
transformers with voltage regulators supplying a common load bus.
FIGURE 6.16 A load-balancing control
scheme for three parallel transformers with load tap changers.
If the three transformer impedances
equal and if the transformers are set on the proper tap positions,
the transformer secondary currents will all be in phase with the load
current and there will be no current unbalance.
If one or more transformer is set on
the wrong tap, circulating currents will flow in all three
transformers. The principle of operation of the load-balancing method
is to separate each of the transformer secondary currents into a load
current component and a circulating-current component. The
transformer secondary currents flow through current transformers,
labeled CT 1, CT 2, and CT 3 in Figure 6.16.
The currents at the CT secondaries
split into two paths at each of the CT secondary windings. Path 1 (to
the right) goes through a set of auxiliary transformers, labeled CT
4, CT 5, and CT 6. The secondaries of the auxiliary CTs are connected
in series, forcing the currents in all three primary windings equal
one another, each being one-third of the total load current. By
default, the unbalance-current components must flow in path 2 to the
left.
Each of the circulating-current
components (also called unbalanced current components) flows through
an inductive reactance element, called a paralleling reactor. The
paralleling reactors are labeled jX in Figure 6.16. In general, the
unbalance-current components of the three transformers are unequal.
The voltages developed across the
paralleling reactors are added to the sensed voltages at the
secondary windings of the main transformers, which are used to
control the movement of the tap changers.
If transformer 1 is on a higher tap
position than transformer 2 or transformer 3, the unbalanced currents
flowing through the parallel reactors increase the sensed voltage at
transformer 1 and reduce the sensed voltages at transformers 2 and 3.
This causes transformer 1 to lower its
taps and transformers 2 and 3 to raise their taps. If transformer 1
is on a lower tap position than transformers 2 and 3, the unbalanced
currents flowing through the parallel reactors decrease the sensed
voltage at transformer 1 and increase the sensed voltages at
transformers 2 and 3. This causes transformer 1 to raise its taps and
transformers 2 and 3 to lower their taps.
TRANSFORMER GAS IN OIL ANALYSIS BASIC INFORMATION AND TUTORIALS
Various research organizations, such as
Westinghouse Electric Corporation, Analytical Associates, Inc., that
did extensive research in the 1970s quickly led to the widespread use
of dissolved gas-in-oil analysis as a predictive maintenance tool
[4]. There is also an extensive bibliography on this subject found in
IEEE Std. C57.104–1991 [5].
The basic theory is straightforward:
Transformer dielectric fluids are refined from petroleum and are very
complex mixtures containing aromatic, naphthenic, and paraffinic
hydrocarbons. At high temperatures, some of these molecules break
down into hydrogen plus small hydrocarbon molecules such as, methane,
ethane, ethylene, acetylene, propane, and propylene. This process is
known as cracking.
The kraft paper materials that are used
to insulate transformer windings are made up of cellulose. At high
temperatures, cellulose oxidizes to form carbon dioxide (CO2), carbon
monoxide (CO) and water (H2O). High concentrations of CO2 and or CO
are indications of overheated windings.
All of the breakdown products are gases
that dissolve readily in transformer oil in different concentrations,
depending on the specific gas and the temperatures that produce them.
By taking samples of transformer insulating oil, extracting the
dissolved gases and doing a quantitative analysis of the various
gases in the samples through gas chromatography, it is possible to
infer the temperatures at the sites where these gases were produced.
At temperatures below 150°C,
transformer oil starts breaking down into methane (CH4) and ethane
(C2H6). At temperatures above 150°C, ethylene (C2H4) begins to be
produced in large quantities while the concentration of ethane
decreases.
At around 600°C, the ethylene
production peaks while the concentration of methane continues to
increase. Acetylene (C2H2) production starts at around 600°C and
methane concentration peaks at 1000°C. Hydrogen (H2) production is
not significant below 700°C and continues to increase along with
acetylene at temperatures above 1400°C.
Therefore, the relative concentrations
of the key gases change over a wide range of temperature. This is
basis for the application of dissolved gas in-oil analysis for
predictive and diagnostic use. An approximate formula uses the ratio
of C2H4/C2H6 to derive the temperature of oil decomposition between
300°C and 800°C:
T(°C) = 100 C2H4/C2H6 + 150
The so-called Rogers ratio method takes
the ratios of several key gases into account to develop a code that
is supposed to give an indication of what is causing the evolution of
gas. The codes for the four ratio method are given in Table 8.2. A
fairly detailed diagnosis of transformer trouble can be derived from
various combinations of codes, shown in Table 8.3.
The diagnoses shown above were derived
from empirical observation. The problem with the four-ratio Rogers
code is that a code generated from the gas concentrations will often
not match any of the ‘‘known’’ diagnoses.
So like a rare disease with strange
symptoms, many cases of transformer trouble cannot be diagnosed at
all using this method. Another method, called the three-ratio method,
sometimes works when the four-ratio method does not.
In the three-ratio method, the values
of A, B, and C are given in Table 8.4 with the corresponding
diagnoses for the various combinations given in Table 8.5. Not only
are the ratios of the key gases important, but the total quantity of
dissolved gas and the rate of increase are also important factors in
making a diagnosis. One of the criteria for making a judgment call is
the total combustible gas concentration. The combustible gases
include H2, CH4,
C2H4, C2H6, C2H2, which are produced by
oil decomposition, and CO, which is produced by cellulose
decomposition. Each utility has a different philosophy and a
different threshold for concern.
Table 8.6 gives one set of guidelines
based on good utility practice that is useful for determining the
overall health of a power transformer based on the total
concentration of combustible gases.
It is generally accepted that if the
rate of combustible gas generation exceeds 100 ppm per day on a
continuing basis, or if the presence of C2H2 exceeds 20 ppm, then
consideration should be given to taking the transformer out of
service to perform additional tests and inspection.
IEEE Std. C57.104-1991 Table 3 also
provides a set of actions based on the total dissolved combustible
gas (TDCG) concentrations as well as the daily rate of TDCG
production.
According to the IEEE Guide, a rate of
30 ppm per day is the threshold for considering removing the
transformer from service. Oil samples are taken from the bottom drain
valve in a sealed syringe to prevent the dissolved gases from
escaping.
The samples are sent to a chemical
laboratory where the dissolved gases are extracted from the sample
under vacuum and analyzed using a gas chromatograph. The results are
reported as ppm dissolved in oil.
PARALLEL OPERATIONS OF TRANSFORMER PRIMER INFORMATION
The theoretically ideal conditions for
paralleling transformers are:
1. Identical turn ratios and voltage
ratings.
2. Equal percent impedances.
3. Equal ratios of resistance to
reactance.
4. Same polarity.
5. Same phase angle shift.
6. Same phase rotation.
Single-Phase Transformers
For single-phase transformers, only the
first four conditions apply, as there is no phase rotation or phase
angle shift due to voltage transformation.
If the turns ratio are not same a
circulating current will flow even at no load. If the percent
impedance or the ratios of resistance to reactance are different
there will be no circulating current at no load, but the division of
load between the transformers when applied will no longer be
proportional to their KVA ratings.
Three-Phase Transformers
The same conditions hold true for three
phase transformers except that in this case the question of phase
rotation and phase angle shift must be considered.
Phase Angle Shift
Certain transformer connections as the
wye-delta or wye-zigzag produce a 30º shift between the line
voltages on the primary side and those on the secondary side.
Transformers with these connections cannot be paralleled with other
transformers not having this shift such as wye-wye, delta-delta,
zigzag-delta, or zigzag-zigzag.
Phase Rotation
Phase rotation refers to the order in
which the terminal voltages reach their maximum values. In
paralleling, those terminals whose voltage maximums occur
simultaneously are paired.
Power Transformer Practice
The preceding discussion covered the
theoretically ideal requirements for paralleling. In actual
practice, good paralleling can be accomplished although the actual
transformer conditions deviate by small percentages from the
theoretical ones.
Good paralleling is considered
attainable when the percentage impedances of two winding transformers
are within 7.5% of each other. For multi-winding and
auto-transformers, the generally accepted limit is 10%.
Furthermore, in power transformers of
normal design the ratio of resistance to reactance is generally
sufficiently small to make the requirement of equal ratios of
negligible importance in paralleling.
When it is desired to parallel
transformers having widely different impedances, reactors or
auto-transformers having the proper ratio should be used. If a
reactor is used it is placed in series with the transformer whose
impedance is lower. It should have a value sufficient to bring the
total effective percent impedance of the transformer plus the reactor
up to the value of the percent impedance of the second transformer.
When an auto-transformer is used, the
relative currents supplied by each transformer are determined by the
ratio of the two sections of the auto-transformer. The
auto-transformer adds a voltage to the voltage drop in the
transformer with the lower impedances and subtracts a voltage from
the voltage drop in the transformer with the higher impedance.
Auto-transformers for use in paralleling power transformers are
specially designed for each installation. The wiring diagram showing
the method of connecting the auto-transformer is usually furnished.
In general, transformers built to the
same manufacturing specifications as indicated by the nameplate may
be operated in parallel.
Connecting transformers in parallel
when the low voltage tension is comparatively low requires care that
the corresponding connecting bars or conductors have approximately
the same impedance. If they do not, the currents will not divide
properly.
Information Courtesy of ABB Power
Transformers
Subscribe to:
Comments (Atom)
Previous Articles
-
▼
2012
(166)
-
▼
August
(13)
- SINGLE PHASE PAD MOUNTED TRANSFORMER PARTS BASIC I...
- POWER TRANSFORMER RATING, LOSSES AND EFFICIENCY BA...
- THREE-PHASE DISTRIBUTION TRANSFORMERS PARTS BASIC ...
- YY AUTO 3Ø / NEUTRAL = PRIM YES-SEC NO AUTO TRANSF...
- DELTA – DELTA (ΔΔ) CLOSED / NEUTRAL = PRIM NO-SEC ...
- COMMISSIONING, MAINTENANCE AND REPAIR OF POWER TRA...
- IN SERVICE TESTING OF POWER TRANSFORMERS BASIC INF...
- TRANSFOMER POWER FACTOR/ CAPACITANCE MEASUREMENT B...
- POWER TRANSFORMER THERMAL STABILITY TEST BASIC IN...
- POWER TRANSFORMER DIELECTRIC TESTS TYPES BASIC INF...
- POWER TRANSFORMER AUTOMATIC TAP CHANGER CONTROLS B...
- TRANSFORMER GAS IN OIL ANALYSIS BASIC INFORMATION ...
- PARALLEL OPERATIONS OF TRANSFORMER PRIMER INFORMATION
-
▼
August
(13)









